Your university is holding a fund-raiser and will be hiring a band to entertain spectators.  You have been selected to serve as the event project manager and have created a Work Breakdown Structure and duration estimates for the activities involved in site preparation for the event. Construct a network activity diagram based on the following information:

  1. Conduct both a forward and backward pass using AON notation.  What is the estimated total duration for the project?
  2. Identify all paths through the network.  Which is the critical path?
  3. Which activities have slack time?
  4. Identify all burst activities and merge activities.

Activity II  – Given the following information, answer the questions about this project:

  1. Draw the network as a Gantt chart.
  2. What is the critical path?  Which activities have slack time?
  3. What would happen if activities B and D each took 5 extra days to complete instead of the expected duration?  How would the critical path change?

The post Activity 5 | Management homework help appeared first on homeworkcrew.com.



Source link

Thanks for installing the Bottom of every post plugin by Corey Salzano. Contact me if you need custom WordPress plugins or website design.

Looking for a Similar Assignment? Our ENL Writers can help. Get your first order at 15% off!

Order

Hi there! Click one of our representatives below and we will get back to you as soon as possible.

Chat with us on WhatsApp
%d bloggers like this: